Battelle Saves $270,000 Using Wire Saw for Radiological Decontamination & Decommissioning


Read this job story in printable pdf format

Wire saws are ideal for removing large sections of heavily reinforced concrete in pulp and paper mills, steel mills, bridges, dams, power plants and for cutting concrete in any area where space is restricted. Battelle and the U.S. Department of Energy used the wire saw for decontamination and decommissioning of radioactive concrete due to its capability to perform cutting with low noise levels, no vibration and no dust.

The Problem

The first privately-owned research reactor built for radioactive material and reactor core studies at Battelle is now part of a Department of Energy (DOE) program involving radiological decontamination, decommissioning and restoration. The United States Department of Energy contracted with Battelle Memorial Institute to perform environmental restoration on Battelle's JN-3 facility at a Battelle Research Park near West Jefferson, Ohio. Battelle performed atomic energy research including the fabrication of uranium and fuel elements, reactor development, submarine propulsion, fuel reprocessing and safety studies of reactor vessels for DOE and its predecessor agencies from 1943 through the mid-1980's.

The JN-3 reactor was built in 1955 and operations were shut down in 1974. In 1975 the reactor was decommissioned to a restricted level using the regulatory limits required at the time. The original decommissioning project included the removal of the fuel and water used in the reactor operation. This decommissioning brought the building to near-free release levels. Twenty-five years later, the instrumentation to detect residual radiation has improved dramatically, allowing lower regulations than the release levels required. At the present time, DOE and Battelle are working under a shared cost program to return this facility to a condition suitable for use and/or release without any radiological restrictions.

This phase of the Battelle Columbus Laboratories Decommissioning Project was intended to reduce the minimal contamination in the building to the present release levels for use without radiological restrictions. Most of the remaining low radiation levels monitored in the building are from the irradiation of metals in the reactor walls, bioshield and other structures. They do not present a health hazard for Battelle, the workers or the public. However, the As Low As Reasonably Achievable (ALARA) principles Battelle is working under for this DOE project demand the building reach free-releasable radiation levels. In order to reach this level, Battelle removed the massive concrete structures, such as the reactor's bioshield, and miscellaneous contamination from this radioactively "cold" building before it was demolished.

The JN-3 building on Battelle's West Jefferson North site was remediated through removal and disposal of the radioactively irradiated bio-shield. The bio-shield was built of high-density six-foot-thick concrete with carbon steel reinforcement to protect personnel from high levels of radiation produced during the reactor's operation. The manual removal of such a large structure would have required expending considerable time, effort and possible worker exposure. Battelle needed a better alternative. "We constantly search for more advanced technologies to aid in the remediation process and then back that up with continuous improvement," stated Carl Brenner, Battelle's JN-3 Project Manager. "DOE recommended a concept called Accelerated Schedule Technology Deployment (ASTD) to help advance the technology," he added. As a result, Battelle proposed the use of diamond wire sawing to reduce the cost of the bio-shield removal while also facilitating the necessary radiological control during removal and disposal.

Battelle accepted bids from contractors with expertise in wire sawing and selected Cutting Edge Services Corp. "This is a critical job that requires cutting expertise, innovation and problem-solving capability," said Battelle's Support Engineer Cidney Voth. "I have worked with Cutting Edge President, Tim Beckman, for a number of years at other sites and found him qualified for this task in the selection process."

The Solution

Cutting Edge employees completed 40 hours of training in order to work in this radioactive environment. Training included radiation worker training, security and orientation training, bioassay and dosimetry operations, and procedure/work instruction orientation. The contract assumed that each worker would spend 2 hours per day involved in dress-in/dress-out activities as well as daily operational meetings. All the work was performed in compliance with OSHA (Occupational Safety and Health Act) and Battelle Safety and Health requirements.

The scope of work also included the removal of a non-radioactive 29 x 24 x 2 foot-thick wall and 4 x 9 x 4 foot-high pedestal inside the bio-shield. A Brokk hydraulic hammer or "rubble maker" was used for this demolition because the wall was non-radioactive and the operation could be carried out in less time. However, it became apparent that quicker was not better! The hammering created large amounts of dust that had to be controlled with mist spray to reduce the air-borne dust exposure. The water then had to be collected and disposed in a radioactively controlled area causing additional challenges to the Battelle/Cutting Edge team.

The next challenge was to remove the remaining 12,000 cubic feet of concrete that made up the bio-shield structure. Holes were core drilled at strategic locations of the concrete structure so that the diamond wire could be fed through in order to complete the loop of diamond wire before cutting could begin. The diamond wire is a multi-strand cable with diamond segments threaded on it that is looped through a series of pulleys and is continuously pulled through the concrete. Since virtually no concrete structure or cross-section is too large to cut, wire saws are used whenever other cutting methods are impractical.

The Cutting Edge team had to wire saw the concrete wall into 5-10-ton blocks that could be lifted out by the overhead 10-ton crane. The target weight for each block was 17,000 pounds and 64 blocks were removed before the project was completed. The bio-shield consisted of two types of concrete. The standard concrete was 170 pounds per cubic foot and those blocks averaged 8 tons. The Barytes concrete had a higher density of 220 pounds per cubic foot and those blocks averaged 9 tons. Four diamond wire technicians used two wire saws and two hundred feet of 11-mm and 15-mm diamond wire to cut a total of 12,000 cubic feet before the project was completed. The operators began with the removal of the top T-shaped concrete and then began cutting sections free starting from the top.

The Result

The diamond wire has many advantages in addition to the productivity and time efficiency in dismantling large concrete structures. An operating wire saw has low noise levels and because water is used to cool the diamond segments, little, if any, dust is generated during the cutting operation. In addition, wire sawing does not weaken the surrounding structure because there is no vibration and thus the stability of the remaining concrete is not affected. Hammering of the concrete introduces the possibility of making the radioactive material in the concrete unstable, which can be a major risk. Finally, only a small area of the one-inch diameter wire saw comes in contact with the radioactive material minimizing clean-up operations. From a radiological control standpoint, this technology provides a more efficient material disposal, more effective contamination control and better personnel exposure control.

Another key advantage that was the direct result of wire sawing was much lower water usage. Because the water from the cutting operation had to be handled as radioactive material, the disposal of large quantities posed a difficult challenge for Battelle and Cutting Edge. In the first few days of sawing, 1,000 gallons of water per day were required. Though this is not unusual, the disposal of nearly 55-gallon drums of contaminated water per day was unacceptable. Shipping costs for 55-gallon drums were $8 per cubic foot plus $20 per drum.

Cutting Edge devised a water recycle system that removed material from the radioactive water. The recycle system allowed the sediment to settle out of the water so that the water could be recycled. Only the resulting sediment needed disposed of as radioactive waste, and the usage of fresh water dropped to 50 gallons per week!

Once the eight-foot-thick concrete sections are lifted out by crane they were lowered and then wrapped in a special protective yellow wrapping by Battelle workers for transport to a DOE-approved disposal site in Utah. Each concrete block was numbered sequentially and the weight was displayed to facilitate transportation and later loading.

This type of work has paved the way for future projects of this caliber. A critical mission of the DOE is the restoration of public and private facilities and sites contaminated during the course of work for the federal government. The successful use of the wire saw on this project could result in other radiological decontamination, decommissioning and restoration projects under the DOE.